Chief Secretary Reviews Construction of Kota-Bundi Greenfield Airport, Completion Target 4 October 2027
RPSC RASDIPR RajasthanSource: DIPR Rajasthan
1
Why in News
- Chief Secretary V. Srinivas reviewed the progress of construction works of the Kota-Bundi New Greenfield Airport at the Secretariat in Jaipur on Thursday.
- The review was held on 5 November at the Shasan Sachivalaya, Jaipur, where the Chief Secretary directed officials to complete the work within the fixed timeline through mutual coordination.
- He directed that all works, including the runway, terminal building and ATC tower, be executed in parallel rather than sequentially.
- The construction of the airport is proposed to be completed by 4 October 2027, which is the deadline set at this review meeting.
2
What is the issue
- The review concerns the Kota-Bundi New Greenfield Airport, a new greenfield airport project in Rajasthan whose construction progress is being monitored at the level of the Chief Secretary.
- A greenfield airport is built on a fresh, undeveloped site rather than by expanding an existing airport, which requires coordinated execution of runway, terminal, ATC and support infrastructure.
- The Chief Secretary stressed parallel execution of the runway, terminal building and ATC tower, indicating that sequential working is seen as a risk to the 2027 deadline.
- The project involves multiple stakeholders: the Civil Aviation Department, the Airport Authority of India, the Energy Department and other related departments whose senior officers attended the meeting.
- The airport is designed around a passenger terminal building of 20,000 sq m with an annual capacity of 20 lakh passengers, making it a medium-scale modern terminal.
- Passenger facilitation features include 14 check-in counters, 9 self check-in kiosks, an automated baggage handling system and baggage claim carousels.
- A G+3 technical block and a fire station are planned for a modern air traffic control system, showing the safety and technical dimension of the project.
- Sustainability is built into the design through a 1 MWp ground-mounted solar power plant and a 250 KLD MBBR-based sewage treatment plant with zero discharge.
- Connectivity and passenger convenience are addressed through a 6-lane approach road, parking for 300 cars and 70 taxis, and an EV charging station.
The full analysis is in the app
This page is the summary. The detailed analysis of this story covers:
What is the statusWhat are the challengesWhat measuresWhat lies aheadImportant Data PointsBackgroundKey Important PointsPrelims RelatedMains RelatedImportant WordsKey conceptsPrevious year questions